hi
I am a junior eng and need some help to determine if what i am doing is correct
I am checking if a PSV that is already existing on a contactor vessel(natural gas) is sized correctly. I am ckecking the sizing for fire case(wetted and unwetted) water is removed form natural gas.
i am checking fired case(wetted) for the water, I am not checking for gylcol since i m assuming this will degarde at high temperature. I am also doing unwetted cals for the natural gas.
PLease advice me if i am going in the right direction.
Thanks