Hi everybody !!
I'am simulating an LPG extraction unit from Natural Gas in Aspen Hysys Software but the deethanizer don't want to converge .
The specification for the deethanizer are :
Component recovery propane 0.93 mole% in reboiler
component ratio methane + ethane / propane 1e-5 in reboiler
HELP please !!
A copy of simulation has been attached !
NB :I'm using HYSYS V8.6;
I created a Mega file cos i couldn't upload the hysys file :
https://mega.co.nz/#!9oUhwLJI!a2ghkjT2B22Mw_DdqH6sSoxDPnFv-db8bNuEDXVQDZ0