Blowdown Orifice Plate Installation
#1
Posted 10 April 2015 - 09:11 AM
#2
Posted 10 April 2015 - 09:51 AM
Ayman,
Because the BDV is normally closed, to prevent the accumulation of any liquid at either side of the valve especially at downstream, the set of BDV and following RO should be in horizontal position with BDV at high point that will lead to free drain at upstream/downstream lines of the valve...
Edited by fallah, 10 April 2015 - 09:52 AM.
#3
Posted 10 April 2015 - 10:02 AM
@ Fallah,
Many thanks for your prompt answer.
We will check the piping design.
Regards
Ayman
#4
Posted 15 April 2015 - 05:00 AM
hi the attached paper may assist you on this
flarenuf
Attached Files
#5
Posted 20 April 2015 - 05:00 AM
Many Thanks flarenuf.
Similar Topics
Plate Fin Heat ExchangerStarted by Guest_shazzad1613_* , 23 Mar 2024 |
|
|
||
Blowdown Ro SizingStarted by Guest_T_bag_* , 28 Dec 2023 |
|
|
||
Flow Element / Orifice With 2 Transmitter SignalStarted by Guest_nguyenmd147_* , 01 Dec 2023 |
|
|
||
Controlled Type Blowdown Through Vent Stack, Reach Mach 1Started by Guest_x127127@hotmail.com_* , 16 Dec 2017 |
|
|
||
Requirement For Hydrogen (Pressurised) Gas Storage BlowdownStarted by Guest_panagiotis_e_* , 30 Nov 2023 |
|
|