Jump to content



Featured Articles

Check out the latest featured articles.

File Library

Check out the latest downloads available in the File Library.

New Article

Product Viscosity vs. Shear

Featured File

Vertical Tank Selection

New Blog Entry

Low Flow in Pipes- posted in Ankur's blog

Off Spec Tank Requirement In New Projects


This topic has been archived. This means that you cannot reply to this topic.
1 reply to this topic
Share this topic:
| More

#1 rajprocess

rajprocess

    Veteran Member

  • Members
  • 34 posts

Posted 14 September 2015 - 10:22 AM

Dear Forum Members,

 

what is the requirement of offspec tank in new projects?

 

For example if we want to develop a off spec tank scope for new MTBE plant with 1000KTA.

 

1. what is the requirement for no of run down tanks?

2. What is the requirement for off spec tank ( volume)?

 

The scope may change from plant to plant and how we operate, but i am looking for general best practices and even for any design standards.

 

i appreciate if some one can give a insight/explanation to start with this activity.

 

Thanks and Regards,

 



#2 Bobby Strain

Bobby Strain

    Gold Member

  • Members
  • 3,529 posts

Posted 14 September 2015 - 04:10 PM

You should discuss this with the process licensor. There is no single answer without much more information.

 