Hi,
I am currently completing my final year design project on a TEG regeneration still column for an offshore installation.
I have a few questions regarding some aspects of the design and the validity of some of my procedure.
1. I have read that most setups have the still column directly bolted onto the reboiler through a flange. To my understanding, a flange is determined by its class (150#, 300# etc), and in the case of the still column operating at more or less atmospheric pressure, I would guess the flanged connection between the column and the reboiler would be a 150# class.
From my understanding, a column out in the open has skirts and is bolted to the ground. The specifics of the skirt and bolts would dependent on factors such as weight load (bending moment, internals of column, externals, wind load etc). How would I apply this to the flanged connection of my still column to the reboiler? Is it even necessary?
2. For the reflux coil located at the top of the reflux column, I cannot find much specific guidelines on its sizing, and would like to validate by methdology. I took a U value of 170kW/m2K as recommended by PTS (or DEP). This gave me a required surface area of 6.2m2.
I assumed that I would require 25 coils (assumed to be tightly packed, and completely horizontal), and hence found that I would require a surface area of 0.25m2 per loop. Using the nominal pipe sizes, I would then calculate specifics such as internal an external diameter of coil, length and height of coil from top to bottom.
This gave me the following results
NPS = 2 inches
inner diameter of coil = 0.36m
outer diameter of coil = 0.48m
distance between column wall and coil = 0.086m
I don't know if these values are considered acceptable, or if my assumptions are reasonable. I have also yet to work out the distance required between the liquid collector and distributor between the top of the bed and the reflux coil, I am just guessing it would be typical ranges dependent on the type of distributor , correct me if I am wrong about this.
3. I am not too sure if I havent been looking hard enough, since my column is too small for manholes, I would require flanges around for installation and maintenance of internals. I am under the impression I would require flanges at the top of the column above the reflux coil, one at the feed chamber, and one obviously at the reboiler connection. Would there be a specific rule on the minimum required distance between the flange connections and the Torispherical and its "flange/skirt". I am going to guess the middle and bottom flange can be anywhere reasonable, and its distance to internals such as distributors and packing support should not effect anything.
In summary, I am having issues finding the overall height of my column due to spacing of internals, unsure of reflux coil sizing, and also connection between reboiler and column.
For reference, my columns process requirements is as followed:
column internal diameter = 0.65m / 25.6 inches
random bed packing = 1.05m below feed, 1.5m above feed (PTS/DEP procedure).
Sorry for the lengthy post. I am in desperate need of some help/clarification, and any I would be thankful if I could get some advice. Apart from the process design requirements, the mechanical design have proven to be very vague and difficult.
Thanks and Regards,
speakas
Edited by speakas, 24 October 2016 - 02:31 PM.