Newest Articles
ChExpress-March 4, 2010
ChExpress-February 18, 2010
ChExpress-February 4, 2010
ChExpress-January 21, 2010
ChExpress-January 7, 2010
ChExpress-December 8, 2009
ChExpress-November 10, 2009
Energy Efficient Hot and Cold Water
Electrical Process Tomography
Biodiesel: The Road Ahead
Methanol Plant Capacity Enhancement
Plate and Frame Heat Exchangers: Preliminary Design
Compressor Surging Under Control
Plant and Equipment Wellness, Part 1: Observing Variability



cheplusbannerbig.gif (7470 bytes)

Methanol Plant Capacity Enhancement

Published October 15, 2007

Reactor Catalyst Charging

This was the first reactor of its kind at GNFC with spiral wound coils within the shell.
 The catalyst is to be charged on the shell side, while the cooling medium (boiler feed water) flows in the tubes via thermosiphon.  During the startup, the boiler feed water circulation pump maintains the water circulation.

As shown in Figures 4 and 5, the reactor coils are supported at both the ends by six support strips moving radially outward from the central mandrill.  This divides the cross section of the reactor into six equal parts.  These were taken as the basis for charging the catalyst and numbered from 1 to 6 inside the reactor.  

methanol_plant_debottleneck4.gif (51467 bytes)
Figure 4: Internal View of the Isothermal Reactor
methanol_plant_debottleneck5.gif (31817 bytes)
Figure 5: Top Internal View of the Isothermal Reactor

Two catalyst charging nozzles were used with hoppers and 2 ½” dia flexible hoses for charging the catalyst - SACK WISE under the supervision of Linde.  A table was prepared to log the number of bags charged per round and the subsequent dip achieved, which showed the packing uniformity.  This proved to be a very successful method of charging with good packing density with less than 20 mm of variation in the final height adjustment.  A flat and heavy plumb with strong cotton thread was used for taking the dip.

Approximately equal quantities of 20 kg balls/catalyst were filled in HDPE sacks before the start of loading.  About 5.2 m3 alumina balls were filled first in four rounds of sack charging.  The catalyst bed was leveled so that the balls were just inside the tube coiled bundle.  The first dip of catalyst was taken after charging almost half of the catalyst. Thereafter, while monitoring the height, charging continued to completion over approximately two (2) days.

Commissioning activities

The synthesis loop was made available earlier than the distillation loop (6 ½ days) while the total shutdown period was compressed to 8 days by effective identification of the priority of each job.  The effectiveness of the pre-commissioning activities was evident during post-commissioning.  There were no plugged strainers, control valves by-passing, nor false signals during or after the startup of the plant. Re-commissioning of the plant was completed in less than 4 days time.  While, the distillation section modifications were being completed, the synthesis loop pre-commissioning activities were completed.  While the catalyst heat up and reduction was proceeding, crude methanol production was coming online.                       

Peak production levels for the plant were achieved while testing the plant at different feed gas mixtures. The plant has met all process guarantees. Of particular interest has been an improved yield of methanol due to a higher conversion rate and stable reaction conditions.  Less by-product formation has led to a reduction of loading in the distillation section.

Conclusion

From this experience, we see that the plant capacity can be increased by understanding the basic principles of reaction kinetics and unit operations.  Through integration of technology and the use of improved catalyst, this little plant had been transformed into a giant producer.  Proper planning of critical activities like catalyst charging, pre-commissioning of loops, commissioning and guarantee test runs can ensure success.

< previous page

Authors:

CD Bhakta – Chief Manager (Projects) at GNFC Ltd.
Mr A. I. Shaikh – Senior Manager (Projects) at GNFC Ltd.

YN Patel – Senior Manager (Projects) at GNFC Ltd.
Mr S. J. Darjee – Senior Manager (Process) at GNFC Ltd.

Please direct inquires to:

methanol_plant_debottleneck_email.gif (1878 bytes)

 


ChE Plus Subscriber - Click Here for a Printable Version

Fill out your email address to
receive notification of site updates
and instantly receive five technical
questions and answers
!
Email Address:
First Name:
Last Name:

State:

Country:

Industry:

Position:

Signup Remove