|
Published October 15, 2007 Reactor Catalyst Charging This was the first reactor of
its kind at GNFC with spiral wound coils within the shell. As shown in Figures 4 and 5,
the reactor coils are supported at both the ends by six support strips moving radially
outward from the central mandrill. This
divides the cross section of the reactor into six equal parts. These were taken as the basis for charging the
catalyst and numbered from 1 to 6 inside the reactor.
Two catalyst charging nozzles
were used with hoppers and 2 ½ dia flexible hoses for charging the catalyst - SACK
WISE under the supervision of Linde. A table
was prepared to log the number of bags charged per round and the subsequent dip achieved,
which showed the packing uniformity. This
proved to be a very successful method of charging with good packing density with less than
20 mm of variation in the final height adjustment. A
flat and heavy plumb with strong cotton thread was used for taking the dip. Approximately equal quantities
of 20 kg balls/catalyst were filled in HDPE sacks before the start of loading. About 5.2 m3 alumina balls were filled
first in four rounds of sack charging. The
catalyst bed was leveled so that the balls were just inside the tube coiled bundle. The first dip of catalyst was taken after charging
almost half of the catalyst. Thereafter, while monitoring the height, charging continued
to completion over approximately two (2) days. Commissioning activities The synthesis loop was made
available earlier than the distillation loop (6 ½ days) while the total shutdown period
was compressed to 8 days by effective identification of the priority of each job. The effectiveness of the pre-commissioning
activities was evident during post-commissioning. There
were no plugged strainers, control valves by-passing, nor false signals during or after
the startup of the plant. Re-commissioning of the plant was completed in less than 4 days
time. While, the distillation section
modifications were being completed, the synthesis loop pre-commissioning activities were
completed. While the catalyst heat up and
reduction was proceeding, crude methanol production was coming online.
Peak production levels for the
plant were achieved while testing the plant at different feed gas mixtures. The plant has
met all process guarantees. Of particular interest has been an improved yield of methanol
due to a higher conversion rate and stable reaction conditions. Less by-product formation has led to a reduction of
loading in the distillation section. Conclusion
|
ChE Plus Subscriber - Click Here for a Printable Version