Jump to content



Featured Articles

Check out the latest featured articles.

File Library

Check out the latest downloads available in the File Library.

New Article

Product Viscosity vs. Shear

Featured File

Vertical Tank Selection

New Blog Entry

Low Flow in Pipes- posted in Ankur's blog

Selecting Pipe Schedule


This topic has been archived. This means that you cannot reply to this topic.
5 replies to this topic
Share this topic:
| More

#1 jatinder

jatinder

    Gold Member

  • Members
  • 94 posts

Posted 16 May 2013 - 09:25 AM

Dear All,

 

As a recent graduate and a starter process Engineer, I do lack basic information regarding  the selection of pipe Schedule. I do understand few concepts regarding the pipe schedule for example:

 

Pipe Inner Diameter ID

Pipe ID decreases with increase in Pipe Schedule

Wall Thickness

Pipe wall thickness  increases with increase in Pipe Schedule

 

I also don't have troubles in selecting the pipe Nominal diameter. I understood the concept that it should be chosen in such a way that the velocity of the flowing fluid must remain below the erosional velocity. 

 

Here is the Question:

 

As I know that line sizing and pressure drop calculation is the job of a process engineer but I would like to know who is responsible for selecting the pipe Schedule? Is it also the job of process engineer or some other engineer like (piping or mechanical engineer)

 

Thank you very much,

 

Your answers will be very helpful for me

 

J Singh 

 

 



#2 Steve Hall

Steve Hall

    Gold Member

  • ChE Plus Subscriber
  • 167 posts

Posted 17 May 2013 - 06:33 AM

The answer depends on your situation.

 

For large projects - and established plants - pipe specifications are created. The specifications include a section for each pipe class used in the project or plant. For example: a section is devoted to pipe for low pressure steam, another for compressed air up to 150 psig, etc. Each section spells out its scope, including the fluids it is used for, pressure limit and temperature limit. Shortcut nomenclature is usually used to refer to a section, such as "A1". The process engineer uses this nomenclature when creating the P&ID, incorporating it within the line number, which then ties the pipe specification to the P&ID.

 

The pipe specification includes, for each pipe size in its scope, the wall thickness. For instance, a typical specification will call out:

Pipe:  1/2" to 2" Schedule 80, 3" to 8" Schedule 40, etc. (followed by materials of construction, end connections, and everything else needed to get the exactly correct pipe to the job site). Other portions of the section cover fittings, valves, bolts, supports, branch connections, etc.

 

Your question is who determines the pipe schedule. For the project / plant specification case, this is generally done on an institutional basis meaning that the specifications are well established and proven over time. The project or plant standardizes on the specification to minimize the chance of mix-up, reduce spare parts inventory and reap the normal benefits of standardization. The original determination is most likely done by a piping or mechanical engineer taking into account the service conditions, selected piping material (and its yield stress), supporting span, possibility of the pipe being used to support other pipes or components, possibility of the pipe being subjected to external forces (people walking or stepping on the pipe, for example) and, of course, cost.

 

For isolated projects where there is no plant or project specification already established, it's likely that the project team is limited. You would use your best resource to write the specification and it is not unusual for the process engineer to specify the pipe schedule.



#3 latexman

latexman

    Gold Member

  • Admin
  • 1,680 posts

Posted 17 May 2013 - 07:43 AM

My company is a member in Process Industry Practices (PIP).  Among the many standards they have, are some pretty good pipe specs.  Take a look:

 

http://www.pip.org/



#4 jatinder

jatinder

    Gold Member

  • Members
  • 94 posts

Posted 17 May 2013 - 08:26 AM

Thank you Sir! It was helpful.



#5 sidibouziane

sidibouziane

    Brand New Member

  • Members
  • 9 posts

Posted 17 May 2013 - 08:42 AM

Hi, 

 i guess already explained by by our friends . thanks to all of them.

 

the process engineer is to identify the process itself including the operational parameters..this is your responsibility (P, T, viscosity, timing....) and equipment sizing to these operational parameters. once identified, hand over to mechanical / piping engineers to determine the schedule including other inputs ( piping fixation, exposure to external stresses...)

 

regards 



#6 jatinder

jatinder

    Gold Member

  • Members
  • 94 posts

Posted 21 May 2013 - 03:08 AM

Thanks!






Similar Topics