Jump to content



Featured Articles

Check out the latest featured articles.

File Library

Check out the latest downloads available in the File Library.

New Article

Product Viscosity vs. Shear

Featured File

Vertical Tank Selection

New Blog Entry

Low Flow in Pipes- posted in Ankur's blog

Project Specifications And How To Use Them


This topic has been archived. This means that you cannot reply to this topic.
2 replies to this topic
Share this topic:
| More

#1 F.Mokhtari

F.Mokhtari

    Brand New Member

  • Members
  • 3 posts

Posted 04 October 2016 - 11:37 PM

Dear experts

 

I am currently working as equipment design engineer and purchasers send lots of documents for every single project or tender to be responded. I want to know if any one can refer me to some instructions on how to use these huge amount of received documents. I have listed some topics below:

PMS (Piping material spec)

Pressure vessel spec

Process Design Criteria

Specification for welding

:

:

For example recently I had to design a pressure vessel, which, by its design conditions, no impact test was obligatory. But when I checked the project's piping material spec, I noticed they have added impact test requirement for the vessel's inlet piping. Then I wondered if impact test was also necessary for my vessel or not!

 

Thanks in advance.



#2 Pilesar

Pilesar

    Gold Member

  • Members
  • 1,384 posts

Posted 05 October 2016 - 11:47 AM

The purchaser wants the supplier to comply with their specifications. Specifications become part of the legal contract between purchaser and supplier. In the bidding phase, the supplier calculates the cost of compliance and includes that in their bid. If the bidder takes exception to a specification, this should be noted when the bid is submitted. 'Taking exception' may or may not disqualify a bidder... but it is taken into account during the purchaser's bid review process. After the terms of the purchase are finalized, the supplier is legally obligated to deliver to the agreed specifications.



#3 F.Mokhtari

F.Mokhtari

    Brand New Member

  • Members
  • 3 posts

Posted 18 October 2016 - 01:19 AM

The purchaser wants the supplier to comply with their specifications. Specifications become part of the legal contract between purchaser and supplier. In the bidding phase, the supplier calculates the cost of compliance and includes that in their bid. If the bidder takes exception to a specification, this should be noted when the bid is submitted. 'Taking exception' may or may not disqualify a bidder... but it is taken into account during the purchaser's bid review process. After the terms of the purchase are finalized, the supplier is legally obligated to deliver to the agreed specifications.