Hi,
To perform an Hazop study you need to set up a team of knowledgeable people from different discipline and then investigate all the possible scenarios. You cannot perform it alone .
Coming to my mind is the risk of backflow in case of valves stay open or leaking .
What about the compatibility of material ( chemicals, housing, cartridge,...) ,....
note : pay attention to the cartridges replacement , isolation of equipment , pressure drop before opening the lid , need for lifting equipment , SOP ....
Good luck
Breizh
Edited by breizh, 04 December 2019 - 01:47 AM.
Need Help In Calculating Ammonia Slip In Scr Unit.Started by Guest_Redbull010203_* , 11 Mar 2024 |
|
|
||
Oil Production And Desalting UnitStarted by Guest_Ali4269278331_* , 25 Feb 2024 |
|
|
||
Design Of A Psa Unit For Undergraduate Design ProjectStarted by Guest_LMorgan14_* , 04 May 2021 |
|
|
||
Air-Cooler Heat Exchanger - Unit Vs BayStarted by Guest_pymorty_* , 19 Dec 2023 |
|
|
||
Flare Study And Pump SealsStarted by Guest_Sue N_* , 21 Aug 2023 |
|
|