Latest Content
Latest Community Postings
Recent Blog Entries
Community Downloads
ChExpress Blog
Ankur's Tech Blog
Community Admin Blog
Energy Efficient Hot and Cold Water
Electrical Process Tomography
Biodiesel: The Road Ahead
Methanol Plant Capacity Enhancement
Plate and Frame Heat Exchangers: Preliminary Design
Compressor Surging Under Control
Plant and Equipment Wellness, Part 1: Observing Variability


Share this topic:



banner2.gif (6526 bytes)

Case Studies in Process Plant Accidents

     Accidents happen....that is for sure.  But when the stakes are as high as they are in the chemical industry, every effort must be
made to ensure that diasters are avoided.  One of the best ways to avoid accidents is to learn from others.  Let's take a look at some past accidents that were all too real and derive a simple lesson from each one.

A Temporary Modification That Proved Deadly

     Nypro Factory, Flixborough, United Kingdom in 1974

     A series of six reactors were installed side by side, each installed a little lower than the previous one to allow for gravity flow between them.  The reactors were joined by 28 in. diameter pipe with an expansion bellow on the end of each pipe.

procacc1.gif (11319 bytes)

     The bellows were installed on the short pipe runs to allow for expansions and small movements that typically accompany operating conditions such as those at Nypo (150 0C and 10 bar).  These reactors were usually cooled via brine to jackets on the outside of the vessels.  The brine system had to be taken offline for repairs so city water was used in the interim.  Reactor #5 collapsed soon after, but no significant leak was experienced.

Error #1
     The city water was supplied to the cooling jackets at 9 bar, a pressure higher than the brine system operated under.  A simple material stress analysis may have been able to predict the material's limitations.



 

     A 20 question modification approval form was completed before any modifications were made.  The questions were not answered properly and the form was treated as a formality.  A professionally qualified engineer was not available to review the suggested modification.

Error #2
     Any plant modification should be taken seriously no matter how simple it seems.  All modifications should be approved by qualified personnel.




     While Reactor #5 was being repaired or replaced, the modification that was approved and installed is shown below:

procacc2.gif (8443 bytes)

     Reactor #5 was replaced with a 20 in. pipe with two bends to accomodate the height difference.  The existing bellows were left in place at the ends of the temporary pipe.  The temporary pipe was supported by resting it on scaffolding.

Error #3
     The third error, and most costly, was the lack of physical bracing or support for the pipe.  The original pipe runs were shorter and supported firmly as to minimize the pipe movement and to allow the bellows to operate properly.

 

 

 

Result
     The temporary pipe was allowed to twist and move laterally due to the lack of proper support.  This is a textbook recipe for mechanical failure.  That's exactly what happened in one of the bellows.   Approximately 50 tons of cyclohexane was released, mixed with air, and exploded.   28 people lost their lives.

 

 

 

 

Lack of Concentration of Faulty Design

     An operator was asked to maintain the temperature of a reactor at 60 0C.  The control panel was set up in such a manner that it may have resembled the diagram below:

procacc3.gif (3228 bytes)

     Essentially, the set point should have been established by percentage of the temperature range from 0 to 200 0C.  It's not difficult to guess what happened.  The operator simply set the instrument to 60, which corresponded to a reactor temperature of 120 0C!  The result was a runaway reaction, an overpressurized reactor, liquid release, and injured operators.

Error #1
     The operator simply did not pay attention to what he/she was doing.  The lack of concentration could have resulted in much more serious consequences.

 

 

 

Error #2
     The controller lacked an intuitive operating "feel".  The controller almost begged for an incident such as this to occur.  Apparently, there was no temperature safety device installed on the unit...another easily avoidable error.

 

 

 

Understanding Why Testing is Being Done

     A new storage tank was being filled with water to check for leaks and mechanical stability.  While the testing was being performed, two welders were on top of the tank completing the hand rails for the tank.

Error #1
     The tank was being tested for a good reason...to be sure it is safe.  We cannot know that it is safe until after the testing.   Therefore the welders were on a tank working during a potentially dangerous operation.

 

 

 

     The line used to feed the water to the tank was previously used for transporting gasoline.  Some residual gasoline entered the tank with the water.  Once inside the tank, the gasoline immediately floated to the top.   The welders accidentally ignited the gasoline vapor.  Fortunately, neither welder was seriously injured.

Error #2
     Since the water feed line previously contained gasoline, it should have been flushed briefly to a drain before being used to fill the tank.



 

Scaling Up Is Not Elementary

     Scaling up of chemical processes has resulted in many accidents throughout history.  Designers sometimes fail to realize that increasing the volume of a reactor does not mean that the surface area and heat transfer will increase proportionally.  Consider a cylindrical reactor:

procacc4.gif (8747 bytes)

     After scale up, the volume increased by about 2.7 times the original design.  However, the surface area only increased by 1.9 times the original design.  Consider an example where a reaction was studied in a laboratory.   In the lab, there was no observed rise in temperature so the reaction was deemed "thermally neutral" (which is rare).  When the reaction was moved to the pilot plant level, no cooling supply was added to the reactor.

Error
     The heat loss through the laboratory glassware was 3-6 W/kg 0C.  The reaction produced 2.0 W/kg 0C.   Therefore no temperature change was noted until the reaction scale was increased.




     A combination of an increased reactor size (2.5 m3) and a decreased heat loss rate (0.5 W/kg 0C in the pilot plant) resulted in a runaway reaction.  Fortunately, a relief valve was in place and a serious incident was avoided.

 

     After reviewing these incidents, its easy to see how knowing what caused past accidents can prevent future accidents from happening.  With that in mind, I would urge everyone to read the reference cited below.  Mr. Trevor Kletz assembled a well-written compilation of process plant accidents in his book.  It's a fantastic resource!


Reference:

Kletz, Trevor, What Went Wrong: Case Histories in Process Plant Disasters, 4th Ed., Gulf Publishing Company, 1998, ISBN 0-88415-920-5
www.gulfpub.com/books.html



smalllogo.gif (4001 bytes)
JOIN OUR COMMUNITY

  • Stay up to date on new content
  • Post questions and answers in our forums
  • Access downloads and attachments
  • Read member blogs and start your own blog
  • Connect with members via our friends feature
  • Receive and post status updates