Butadiene Extraction Simulation
#1
Posted 14 August 2010 - 08:36 AM
i have tried to simulate butadiene extraction unit using NMP as a solvent , simulation have partly converged but still having problems. can anybody guided for the problems.here i have attached .hsc file.
pl.see it and guide me.
thxs lot in advance.
mehul patel
#2
Posted 22 December 2010 - 01:28 PM
have you any progress yet?
I will be glad to share completing this simulation with u & anybody else
Edited by ashkan1360, 22 December 2010 - 01:29 PM.
#3
Posted 23 December 2010 - 04:31 AM
dear,
i have tried to simulate butadiene extraction unit using NMP as a solvent , simulation have partly converged but still having problems. can anybody guided for the problems.here i have attached .hsc file.
pl.see it and guide me.
thxs lot in advance.
mehul patel
hi
your hysys version is build 7119 and mine 7020
can you convert it to an older than 7020 ?
#4
Posted 24 December 2010 - 01:39 AM
- Stream 46 (Recycle) must be pre-defined (make the initial estimate);
- Stream 2 needs to be a Recycle stream;
- Stream 15 needs to be a Recycle stream;
- Stream 17 needs to be a Recycle stream;
- Stream 24 needs to be a Recycle stream;
- Stream 29 should be a Recycle stream;
- Stream 37 needs to be a Recycle stream;
- Stream 41 needs to be a Recycle stream;
- Stream 50 must be defined;
- Stream 51 must be defined;
- All process heaters/coolers must have assigned duty and pressure drop, or supply pressure/temperature values for the outlet streams;
- Each tee needs to have specified the flow split ratio.
For loading Hysys cases into older versions of software, one can save the simulation case as an XML file which can be used by previous versions.
#5
Posted 08 January 2011 - 10:47 AM
1,3 Butadiene extraction by NMP solvent is an extractive distillation process and any activity coefficient model in Hysys will not have the effective binary interaction parameters which can support this simulation. I have almost broken my head to converge (it converges very fast) to match the licensor material balance. Hope to get the some positive updates from your side.
#6
Posted 08 January 2011 - 02:52 PM
Dear Mehul,
1,3 Butadiene extraction by NMP solvent is an extractive distillation process and any activity coefficient model in Hysys will not have the effective binary interaction parameters which can support this simulation. I have almost broken my head to converge (it converges very fast) to match the licensor material balance. Hope to get the some positive updates from your side.
Dear sir,
can we share working on this simulation ?
how many years do you have experience in BD plant?
#7
Posted 12 January 2011 - 09:35 AM
Hi,
dear,
i have tried to simulate butadiene extraction unit using NMP as a solvent , simulation have partly converged but still having problems. can anybody guided for the problems.here i have attached .hsc file.
pl.see it and guide me.
thxs lot in advance.
mehul patel
I'm up to start exactly the same process (BASF License) simulation. The work starts tomorrow, I'll let you know how it goes. It will be in AspenPlus V7.2, but converting it into Hysys won't be a big deal,
Cheers
ok
let's start it
#8
Posted 13 January 2011 - 08:19 AM
yes i have 20 years experience in BD plant. yes we can share on it.if there is possibility to get converge it.
Dear Mehul,
1,3 Butadiene extraction by NMP solvent is an extractive distillation process and any activity coefficient model in Hysys will not have the effective binary interaction parameters which can support this simulation. I have almost broken my head to converge (it converges very fast) to match the licensor material balance. Hope to get the some positive updates from your side.
Dear sir,
can we share working on this simulation ?
how many years do you have experience in BD plant?
mehul
#9
Posted 13 January 2011 - 08:29 AM
Dear Mehul,
1,3 Butadiene extraction by NMP solvent is an extractive distillation process and any activity coefficient model in Hysys will not have the effective binary interaction parameters which can support this simulation. I have almost broken my head to converge (it converges very fast) to match the licensor material balance. Hope to get the some positive updates from your side.
sir,
i have converge my acetylene washer column for NMP losses in Wash water separately with thermodynamic model NRTL-SRK , give little bit closer result with my current process perameter. but i have yet difficulty to achieve full simulation.if there is a possibility to complete work with another simulation like CHEMCAD or ASPEN PLUS or PROii then pl.guide me.
#10
Posted 14 January 2011 - 10:36 AM
Dear sir,
can we share working on this simulation ?
how many years do you have experience in BD plant?
Dear Ashkan1360,
I simulated this unit for a student who was supposed to submit her report on sensitivity analysis of Butadiene Extraction unit, may be 2 years back. And now I am working on detailed engineering of the same unit. But I don't have any operational experience of this unit. I remember some correspondences with Aspen Tech regarding this simulation two years back and based on that only I can help you, if you come up with specific query.
#11
Posted 16 March 2011 - 01:57 AM
I'm a chemical engineering student doing a project to design a plant for butadiene extraction from mixed C4 product with NMP solution. Currectly assigned to perform material balance and hysys simulations. I have tried performing material balance and hysys simulations for many days already but still clueless on how to start and what to do. Thus, search online for help. Would you please be so kind to send me the material balance and hysys file you have done with other gentlemen before? Here is the information given to me:
Mixed C4 Feed:
Flow Rate = 12.05 tonnes/hour
Operating Hour = 8300/year
Composition (Wt%)
Methyl Acetylene = 0.4
Propadiene = 0.1
Propane = 0.1
1,3 Butadiene = 46.5
Ethyl Acetylene = 0.1
Vinyl Acetylene = 0.4
1-Butene = 11.0
Cis-2 Butene = 4.1
Trans-2 Butene = 5.4
Iso-Butene = 30.1
Iso-Butane = 0.6
N-Butane = 0.6
Iso-Pentane = 0.6
I would be so real glad and grateful to receive your reply. Any help from anyone is deeply appreciated. Thank you.
#12
Posted 29 May 2011 - 11:28 AM
does anyone have the PFD , P&ID of new BD plant (BASF) ?
#13
Posted 06 June 2011 - 05:18 AM
hi dears,
does anyone have the PFD , P&ID of new BD plant (BASF) ?
hi dear ,,,
be careful i'm gone take your MOCH ,,,
Similar Topics
Dynamic Simulation - SeparatorsStarted by Guest_tomr91_* , 10 Mar 2025 |
|
![]() |
||
![]() Dynamic Simulation After Feed Flow ReductionStarted by Guest_Kakashi-01_* , 20 Mar 2025 |
|
![]() |
||
Prv Vs Extraction Condensing TurbineStarted by Guest_mj311_* , 13 Nov 2024 |
|
![]() |
||
Converting A Static Simulation To Dynamic SimulationStarted by Guest_tomr91_* , 26 Feb 2025 |
|
![]() |
||
Basic Dynamic Simulation Of A Crude Distillation UnitStarted by Guest_tomr91_* , 12 Jan 2025 |
|
![]() |