I'm new

Well,anyhow, these two weeks might be possibly be my last, since the dateline for my final year paper is due next friday.
So a little background info on my project:
My team (of 10 students), are designing an IGCC plant with carbon capturing option. The entire cohort is split to different problem statements, eg, 500 MW production, varying cost of coal, $carbon tax, %carbon capture required. The design project is split into 3 portions, namely, an preliminary design of the entire plant - interim report 1, interim report 2 -an operational and mechanical design of a specific unit operation (seperator/reactor/heat exchanger, of which my subgroup of 3 did the heat exchanger design), and lastly, interim report 3 - which includes everything else. This time around, I'm assigned to a 3 man team doing the economics of the plant.
Having read some of the posts here, and, textbooks, I can only conclude that it is impossible, given the timeframe, and manpower nor expertise, to decently get a reliable cost estimate. Nonetheless, we need to.
Now to get things started, I have tried to cost estimate one of the designs made in interim report 2, namely, an absorber column. From seider's and Peters/Timmerhaus, i understand that there are mainly 3 components to a tower column.
1)cost of shell, including skirt, nozzles, etc.
2)cost of packing, internals
3)cost of auxiliary components.
Specifications:
Column height: 43.4m
Two elliptical head: 2m
Skirt: ~ 4.6m
Column Di ~ 8.55m
Shell thickness: 0.1m (head thickness assumed to be 0.1m as well)
MOC: Stainless Steel 304
Random Packing (0.050m Metal Pall Ring): 31m
The report has no info on nozzle, etc. It has 6 manholes, but no specified size. Now i understand that this is a non-standard size, but i will use the figure provided by seader's nonetheless, to get some figures (which would safe to say, be an underestimate).
Without even proceeding to calculate the cost of component #2,
I calculated F.O.B of empty shell ~ $5066816.8
Then the bare-module cost would be (if i read the FBM = 4.16, vertical pressure vessel?)
That, would give me a CBM ~ $21077957.89 . (21mil, am i reading this right?) Factoring cost index , base 500, project 2011 figures based on best fit from 5 yrs data ~ 571 (can't find any latest figures for 2011) That would give me $22.76mil.
Before even proceeding on to include packing costs:
Huh, are distillation columns supposed to be so expensive? Is it a mis-design problem, or a cost-estimation problem?
Well I hope to move past this manual calculations exercise soon, and proceed on to use Capcost to calculate the rest of the plant, given that only 3 unit operations were actually sized, I see no point in giving an extremely detailed cost estimate for the entire plant, and thus this would only serve as a sample calculation given in the report.
Thank you for your time, and responses once again!
Jon
Edited by du3z, 19 April 2011 - 02:33 PM.