- What is/are process engineering deliverables as per simulation, operation and design?
- What is/are the limitation to the above
Please need details clarification.
Thanks
|
Posted 05 April 2013 - 04:01 AM
Please need details clarification.
Thanks
Posted 05 April 2013 - 08:39 AM
That's a very wide ranging question. Can you be a bit more specific?
What stage of a project are you talikng about:
The process engineering deliverables are different for each of these stages. They are also specific to a given client, who will define what he wants in a scope of work.
When you say "limitations" what do you mean?
Paul
Posted 05 April 2013 - 09:37 AM
I'd agree with Paul, more details are needed.
The deliverables are usually a developing procedure. For example, the PFD is a deliverable at Concept phase, but may be completely reworked, added to, more detailed by the end of the design phase. The same goes for P&IDs in the detailed design to post startup phases.
Posted 07 April 2013 - 07:09 AM
May be I should restructure my question as follow:
What is/are the role of a process engineer at each phase/stage of a project as listed below and what is/are the deliverable at each stage?
Thank you, hope to get these straight from you.
Posted 07 April 2013 - 12:02 PM
done,
Conceptual Design:
1. Feasibility Study
2. Basis of Design
3. Scope of Work for FEED
4. Process Block Diagram
5. Process Description
6. Equipment List
FEED:
1. Basis of Design
2. Process Flow Diagrams (PFDs)
3. Piping & Instrument Diagrams (P&IDs)
4. Line List
5. Equipment List
6. Equipment Process Datasheets (Functional) (Tanks / Vessels / Pumps / Compressors / Package Items)
7. Instrument Datasheets
8. Operating, Control & Safeguarding Philosophy
9. Line Sizing & Hydraulic Report
10. Hazardous Area Classification Drawings
11. Design Review & Design Review Closeout Report
12. Insulation Specification
13. Material Selection Report
14. Relief Valve Sizing and Dossier
15. HAZID Review & HAZID Report
Detailed Design:
1. Design Basis (updated from FEED)
2. Process Flow Diagram (PFD) including Heat & Mass Balance
3. Piping & Instrument Diagrams (P&IDs) (Issued for Construction)
4. Line List
5. Equipment List (includes missing data such as vendor information of vendor packages)
6. Final Line Sizing and Hydraulic Report based on Piping GADs and Isometrics
7. Updated Operating, Control and Safeguarding Philosophy
8. Commissioning Procedure & Plan
9. Plant Operating Manual
10. Updated Material Selection Report
11. 2nd Design Review and Design Review Closeout Report (optional)
12. HAZOP Review and HAZOP Review Closeout Report
Commissioning & Startup:
1. Hydro and Pneumatic Test Loop Diagrams
2. Line Flange Blank Register
3. Commissioning Punch List
4. Standard Operating Procedures (SOPs)
5. Setpoint and Alarm List
6. Controller Tuning Register
7. Red-lined P&IDs for As-Builting
Please explain what do you mean by post startup revamp.
Regards,
Ankur.
Gpsa Engineering Data Book 14 Th Pdf .Started by Guest_guoyinyanliner_* , 03 Apr 2025 |
|
![]() |
||
Chemical Engineering ResourcesStarted by Guest_Pilesar_* , 24 Apr 2025 |
|
![]() |
||
Going Through The Writing Process.Started by Guest_Haywardvek_* , 05 Jan 2025 |
|
![]() |
||
Typical Process Of Platformate Splitter ?Started by Guest_AnbIran_* , 30 Dec 2024 |
|
![]() |
||
![]() Opportunities For Heat Recovery In A Chemical Process PlantStarted by Guest_tanyongboon1_* , 29 Nov 2024 |
|
![]() |