What are the steps and sequence of turndown and shutdown of an Ammonia Plant?
Broadly, as I believe, a planned shutdown starts with reducing load on Ammonia Refrigeration Section and then shutting the Purge Gas Recovery. Then, slowly fuel has to be cut-off (here, Methane is used with Gas Turbine), followed with Feed and Steam.
I would like to know about process considerations and detailed turndown steps with other Unit Ops involved. There could lots of parallel activities which can be done simultaneously - so a summary in the form of flowchart / schedule will be very helpful in understanding
Any assistance in this regard will be useful.