I have configured detailed tray internals in steady state column/internals tab in Aspen hysys. but I am getting choke flood error for all trays that it exceeds 100 percent choke flood. In my process flows, I have exceeded the flow of reflux by 6 kg/hr to match top draw and bottom draw. due to this, I think this is happening., but how to eliminate that error without changing the top flows and reflux flows.
|


Distillation Column Internals
Started by CHEMSTRONG, May 13 2018 11:18 AM
3 replies to this topic
Share this topic:
#1
Posted 13 May 2018 - 11:18 AM
#2
Posted 13 May 2018 - 02:23 PM
I would obtain a solution without tray details. Then rate the trays with one of the vendor programs.
Bobby
#3
Posted 14 May 2018 - 08:09 AM
The tray design should be based on the vapor and liquid load.
#4
Posted 10 June 2018 - 02:42 PM
Is the tray rating utility in HYSYS actually representative of your trays? My plant has a bespoke tray design that cannot be covered by these simple utilities. I utilize the Kister & Haas flooding correlations in a spreadsheet function in lieu.
Similar Topics
![]() Packaging And Gas Velocity In Packed ColumnStarted by Guest_ChemEng_CristianoB_* , 25 Jun 2025 |
|
![]() |
||
Distillation Column Reboiler QuestionsStarted by Guest_AlanC079_* , 07 Jul 2025 |
|
![]() |
||
![]() Distillation Column Top PressureStarted by Guest_halkeshhulk_* , 27 Jun 2025 |
|
![]() |
||
![]() Distillation Column Top & Bottom TemperaturesStarted by Guest_halkeshhulk_* , 09 Jun 2025 |
|
![]() |
||
![]() Distillation Tower Top And Bottom Temperature And PressureStarted by Guest_student55_* , 27 Mar 2016 |
|
![]()
|