hi,
I have an application where i see hydrate formation during blowdown. We want to inject methanol upstream of the blowdown valve during depressurization. there are about 3 blowdown points. also there is one methanol injection point upstream of a recycle control valve. Since all the injection is intermittent, whatt is the effective stratergy for injection. do we take 1 methanol pump per injection point or take multi head pump? since injection points have different initiating events, what will be effective stratergy or philosophy of injecting?