Steam Accumulation Vessel Design Problem

steam accumulation heat transfer buffer time boiler

7 replies to this topic
Share this topic:
| More

#1 Jca123

Jca123

    Brand New Member

  • Members
  • 2 posts

Posted 22 October 2022 - 01:49 PM

Hi all, pretty new to this forum!

Recently graduated and working for a startup company, building pilot plants.

 

Regarding a small side project i was asked to design and size a qteam accumulator vessel.

 

this vessel will be tied into a steam supply line, coming from a boiler.

I,ve got the following information:

 

incoming steam = 400 kg/hr, 5 barg

requested output of accumulator: 400 kg discharge in 10 minutes, 3 barg (2400 kg/hr for 10 minutes)

recovery time= 50 minutes ( 1 full cycle is 1 hr)

i’ve found some info online regarding thid topic, but i hope you guys and gals, could help me.

I know that the surface area of the water in the vessel is very important.

My biggest nightmare is under or overdesign this vessel.

 

Thanks!



#2 Bobby Strain

Bobby Strain

    Gold Member

  • Members
  • 3,529 posts

Posted 22 October 2022 - 03:59 PM

You are not going to get much help from "you guys and gals". We know when you joined the forum.

 

Bobby



#3 Jca123

Jca123

    Brand New Member

  • Members
  • 2 posts

Posted 25 October 2022 - 12:16 PM

What do you Mean?
What's thé Point of this forum then?

#4 Saml

Saml

    Gold Member

  • Members
  • 301 posts

Posted 25 October 2022 - 09:07 PM

 

What's thé Point of this forum then?

 

 

So you don't have to look around the forum to figure out an answer. People here is treated as professionals. That is, one thing is to ask for a second opinion after you show what you did, or answering an specific question that you find difficult. Asking others to do your job is a non starter.



#5 breizh

breizh

    Gold Member

  • Admin
  • 6,334 posts

Posted 25 October 2022 - 11:04 PM

Hi,

Take a look at this resource https://www.spiraxsa...am-accumulators

Consider advice given to you to improve your engineering skill.

Good luck

Breizh 



#6 latexman

latexman

    Gold Member

  • Admin
  • 1,680 posts

Posted 26 October 2022 - 06:46 AM

Jca123,

 

Basically, you repeated your problem statement and said, "help me".  To us, that looks like you did not even try, and you want SGOTI to spoon feed you.

 

No thanks.

 

Engineer up, and do your job!  If you have a specific question, after you research and make a bona fide attempt(s) at a design, please let us know.  Someone should be glad to help.  Personally, I have no experience with steam accumulators, but I will be following, so I can learn.



#7 katmar

katmar

    Gold Member

  • ChE Plus Subscriber
  • 667 posts

Posted 27 October 2022 - 04:28 AM

It will be interesting to see how it works with 333 kg being fed in during the recovery stage (400 kg/h x 50 / 60 = 333) and then 400 kg being removed during the discharge stage.



#8 fallah

fallah

    Gold Member

  • ChE Plus Subscriber
  • 4,951 posts

Posted 27 October 2022 - 05:01 AM

It will be interesting to see how it works with 333 kg being fed in during the recovery stage (400 kg/h x 50 / 60 = 333) and then 400 kg being removed during the discharge stage.

 

Then incoming steam flow rate should be 480 kg/h...right?