Dear brother.
I want to design to collection gas from an unman platform. Used gas turbine driven for gas export compressor.
Please tell me, need or no need change platform from unman to man.
If need the changing, the minimum requirements for man platform.
Thank
|

Help To Gas Collection
Started by manhtien152, Apr 01 2011 08:50 PM
5 replies to this topic
Share this topic:
#1
Posted 01 April 2011 - 08:50 PM
#2
Posted 02 April 2011 - 02:45 AM
Manhtien,
Please elaborate a bit more on the subject. What sort of "gas collection" are you referring to? Is it a production manifold with gathering station, or is it just a gas sample collection?
Either way, the system can be manned or unmanned - depending on what it is designed for.
Please elaborate a bit more on the subject. What sort of "gas collection" are you referring to? Is it a production manifold with gathering station, or is it just a gas sample collection?
Either way, the system can be manned or unmanned - depending on what it is designed for.
#3
Posted 02 April 2011 - 09:35 PM
Thank for reply.
existing is oil platform, now i want to collect gas in it. So that i had design a gas turbine compressor.
Existing is unman platform, but i want to know have some standard about operating for gas turbine compressor in the unman that.
Thank very very much
existing is oil platform, now i want to collect gas in it. So that i had design a gas turbine compressor.
Existing is unman platform, but i want to know have some standard about operating for gas turbine compressor in the unman that.
Thank very very much
#4
Posted 02 April 2011 - 10:18 PM
Configuration in the WHP is:
- HHP separator, test separator, gas export compressor package, dehydration package, fuel gas skid...
I can operating and control all system in the WHP from the other platform (FPSO, FPU..)?
- HHP separator, test separator, gas export compressor package, dehydration package, fuel gas skid...
I can operating and control all system in the WHP from the other platform (FPSO, FPU..)?
#5
Posted 03 April 2011 - 05:10 AM
Yes, that is completely feasible. You can even operate them from onshore, depending on how far you actually are from the mainland. The concept that I have seen in past, when several platforms discharge into the same pipeline, is to have one platform manned and equipped with DCS to monitor and control parameters on all platforms. In one project, I also remember having Offshore DCS operators in the control room located onshore.
#6
Posted 03 April 2011 - 08:16 PM
In this project, i had DCS control in the FPU, distance from WHP to FPU is 4.5 km.
But according to the some expert consulted to me, gas turbine need operator in that platform.
You have some standard or guideline for that please sent to me?
Thank so much.
But according to the some expert consulted to me, gas turbine need operator in that platform.
You have some standard or guideline for that please sent to me?
Thank so much.
Similar Topics
![]() Microsoft Excel Spreadsheets – Chemical Engineering CollectionStarted by Guest_Leopassosfida_* , 04 Oct 2016 |
|
![]()
|
||
![]() Microsoft Excel Spreadsheets – Chemical Engineering CollectionStarted by Guest_Leopassosfida_* , 04 Oct 2016 |
|
![]()
|
||
A Link To A Collection Of Tutorials And Videos On Matlab.Started by Guest_datakid_* , 05 Feb 2010 |
|
![]()
|
||
Plant Data CollectionStarted by Guest_Srikrishna Chaitanya_* , 13 Oct 2009 |
|
![]()
|
||
Dedusting System / Dust CollectionStarted by Guest_breizh_* , 26 Sep 2009 |
|
![]()
|