Jump to content



Featured Articles

Check out the latest featured articles.

File Library

Check out the latest downloads available in the File Library.

New Article

Product Viscosity vs. Shear

Featured File

Vertical Tank Selection

New Blog Entry

Low Flow in Pipes- posted in Ankur's blog

Relief Valve Sizing


This topic has been archived. This means that you cannot reply to this topic.
24 replies to this topic
Share this topic:
| More

#1 Guest_Kiran Parihar_*

Guest_Kiran Parihar_*
  • guestGuests

Posted 15 December 2005 - 12:44 AM

Dear All,
I have a doubt regarding the sizing of Relief Valve for control valve failure case. And hope that in this forum I will be able to clear my mind.
For calculating the maximum flow, I normally take the maximum flow passing through control valve (rated Cv of Control Valve) with bypass closed.
During the discussions we had in our company, it was suggested to also add the flow through the bypass to the maximum flow. I did not agree because of obvious reason that the bypass would be normally closed during the control valve failure and we have isolation valves to remove the control valve for repairing.
All your answers would be highly appreciated

Best Regards

#2 Art Montemayor

Art Montemayor

    Gold Member

  • Admin
  • 5,782 posts

Posted 15 December 2005 - 06:39 PM

Kiran:

I've run into this argument/challenge several times. The logical answer is that it is illogical to expect that an operator could make the mistake of opening the bypass while the control valve has failed in the open position. And that is the only logical manner that one could have both open at the same time.

You are absolutely correct in stating that the reason the manual bypass valve is there in the first place is that it is to be used as a manual operation when doing maintenance on the CV or the CV has failed to open. In both of these events, an operator is expected to crack the bypass and block-in the CV in order to prepare to remove it or repair in situ. If an operator were to open the manual bypass while the CV failed in the open position it would constitute "Double Jeopardy" and would not be a credible design scenario. Both events are not related so the odds of both happening at the same time fall under the double jeopardy description. All design meetings and hazops where I've run into this dilemma have reached the same decision as you: The maximum Cv value of the control valve sets the maximum flow through it and is the basis for the relief capacity.

I wish you had posted this query in the Relief Valve Forum, so it would get the proper exposure.

#3 djack77494

djack77494

    Gold Member

  • ChE Plus Subscriber
  • 1,282 posts

Posted 16 December 2005 - 12:59 PM

I had an interesting thought about this topic. Another situation, though rare, would occur when the control valve is removed for servicing and you are operating using the bypass valve. It might be in any position, including fully open. Should whoever is supposed to be paying attention to its operation become distracted, that situation would be very similar to a failed control valve. For that reason, I would propose that the relief scenario should be based on the LARGER of a failed open control valve OR a fully opened bypass valve. Any thoughts about this?

#4 Art Montemayor

Art Montemayor

    Gold Member

  • Admin
  • 5,782 posts

Posted 16 December 2005 - 01:52 PM

Doug:

You've not only made an excellent mental exercise, but you are absolutely correct as to your evaluation of the manual operation for control purposes. Although most by-passes are usually 1 size below the CV size, it is still possible to have the bypass contributing more flow during your described procedure - all depending on the type of valve and its Cv value.

Once again, your result has shown how a critical worse case can be camouflaged from the perception of those engineers trying to identify the controlling case. It is so very important to explore all possible operational and accidental occurances by carefully detailing a complete explanation of the scope of work.

#5 Guest_Kiran Parihar_*

Guest_Kiran Parihar_*
  • guestGuests

Posted 17 December 2005 - 02:37 AM

Thanks for your replies.
The forum continues to enrich young learning engineers.

#6 kdal

kdal

    Junior Member

  • Members
  • 13 posts

Posted 19 December 2005 - 01:51 AM

I've experience of working for 2 international contractors in the O&G industry and interestingly they both take different views on the subject.

The first approach reflects Doug's previous post - it is feasible for the control valve to be in the normal operation and the bypass valve inadvertantly opened which produces an incremental increase in flow for relief. However it is double jeopardy for both the control valve and bypass valve to be wide open simultaneously.

The other contractor's approach is far more conservative and they make a point to say that the relief rate should be calculated with the control valve and its bypass fully open, to account for "start-up cases". I'm afraid that it doesn't go on to expand on what is meant by start-up cases!

Just thought that it was interesting how there is not a common approach and it very much comes down to the nature/ethos of the organisation for which you work. Does you're employer or perhaps client have a philosophy on this matter?

#7 djack77494

djack77494

    Gold Member

  • ChE Plus Subscriber
  • 1,282 posts

Posted 19 December 2005 - 09:10 AM

My employers tended to "leave open" the development of relief case scenarios to the responsible engineer. I think it very difficult to do otherwise, since I can't imagine being able to enumerate all possible cases in the required detail. Of course, I've seen the lists of potential relief scenarios - this case would start with "CONTROL VALVE FAILURE". But that's it. There was no further guidance. Issues like discussed above were not discussed at all. End result is that it all depends on the experience and judgement of the engineer. Art, I don't want to appear contradictory, but I've often seen bypass valves the same size or even larger than the control valve. My current client, a major in the oil business, insists on the use of BALL valves for their bypass valves; they'll be one size smaller than full line size/certainly not smaller than the control valve. Wonder what their Cv's are?

#8 abhi_agrawa

abhi_agrawa

    Gold Member

  • ChE Plus Subscriber
  • 216 posts

Posted 20 December 2005 - 04:05 AM

I'll just add something about the "start up" cases. Recently I was involved in the commissioning of a plant, where through a Control Valve, the flow of gas was more during the start up as compared to the normal operating case. This was because there was a reaction involved, and during the start up, the reaction was not effective, leading to a relatively large amunt of gas. However, for this scenarion, the control valve was chosen with a large Cv, so that during the start up, the bypass was not operated. The bypass was sized to allow the "normal" operating flowrate when fully opened. The relief valve was sized as per the maximum gas flow rate during the startup.
abhishek

#9 pleckner

pleckner

    Gold Member

  • ChE Plus Subscriber
  • 564 posts

Posted 21 December 2005 - 12:17 PM

The purpose of the by-pass is to operate the process while taking the associated controll valve out of service (for whatever reason). These by-pass lines were never intended to be used for start-up (OK, a generalization but for the most part true). Those who use them for start-up are asking for trouble and it just isn't necessary. Just put the control valve in manual and open/close as needed through the control system.

If the by-pass is to be operated at the same time as the associated control valve then the total flow through both the by-pass and the control valve (fully opened) must be at least analyzed when determining the PSV sizing. Some years ago during a design of HFC facility I put in restriction orifices in the by-pass lines so that they would not be controlling in PSV sizing (yes, these lines were one-size smaller than the associated control valve). The flow was more than enough to allow the process to operate when the control valve was out of service but was restrictive enough during the relief scenario that it was not controlling over a fully opened control valve.

#10 gvdlans

gvdlans

    Gold Member

  • ChE Plus Subscriber
  • 619 posts

Posted 22 December 2005 - 03:20 AM

Phil, good to see you back on the forum.

One approach is to size the relief valve for largest flow through either fully open manual valve or fully open control valve (whichever results in the largest relief flow), and to check that downstream pressure remains below the hydrotest pressure when both control and manual valve are fully open.

Reasoning is that in the highly unlikely, but still credible case that both valves are fully open, there will still not be a loss of containment.

Note that the Cv values of the actually installed valves have to be used and that there should be some system in place to prevent installing of a valve with a higher Cv without checking the relief valves.

#11 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 03 March 2006 - 12:40 AM

May be a bit late, but could not help chipping in my bit.

No one seems to talk of the applicable codes (API 520/521) and design practices/guidelines by majors that are recognised in the industry.

Almost every guideline requires some consideration of the bypass valve being in the open position (along with the CV full open), though the extent of pressurisation allowed for the equipment to be protected varies. I can recall one guideline allowing up to the hydrotest pressure.

May be it is better to be safe than (extra) economical.

Regards

#12 pleckner

pleckner

    Gold Member

  • ChE Plus Subscriber
  • 564 posts

Posted 03 March 2006 - 12:48 PM

I think the previous posts do talk about the scenarios of both a fully opened control valve and the opened by-pass. But if one is made significantly more restrictive than the other (as I had done in one design-see my post below), the relief flow will be governed other less restrictive path and will govern. To put the problem to rest, simply car-seal the by-pass valve closed.

Please note that API RP520 and RP521 are not codes but Recommended Practices. Saying this, they historically represent good engineering practice and thus should be followed as guidelines.

#13 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 07 March 2006 - 02:09 AM

Having a bypass more restrictive than the CV would defeat its purpose. Cv of the bypass (valve full open)should be atleast same as that of the control valve in full open position.

With respect to APIs, the point is noted, these are RPs not codes.
Regards

#14 pleckner

pleckner

    Gold Member

  • ChE Plus Subscriber
  • 564 posts

Posted 07 March 2006 - 12:40 PM

If you want to run your system using your by-pass with no control whatsoever, feel free to do so. That is not what the by-pass is meant to be used for.

I guess we are just going to agree to disagree.

#15 Guest_Kiran G Parihar_*

Guest_Kiran G Parihar_*
  • guestGuests

Posted 07 March 2006 - 11:40 PM

Dear All,

The PSV's can be designed according to client's specification wheather he wants to include or exclude the bypass flow.
But the problems that may arise if we include the bypass calculations will be:

1. PSV oversized for Normal CV failure. (Will this result in chattering??. Comments awaited)

2. Line sizing & Pressure drop calculations for the PSV sized. (And in many cases, we will not be able to meet 3% criteria)

Thanks

Kiran G Parihar

#16 Ritesh Suratwala

Ritesh Suratwala

    Junior Member

  • Members
  • 17 posts

Posted 08 March 2006 - 02:06 PM

I am totally agree that any unnecessory design margin in PSV capacity is not a good engineering practice and will lead to chattering.

And as far as line size is concern, you can not design line size for normal capacity and PSV for rated capccity. Your line size also must be based on rated capacity only. So, I will be concerned about point 1 only and will not bother about point 2.

If I come to main topic, my experince says eventhough it is "Double Jeopardy", selection depends on criticality of process. In LNG plans and Crude refineries, any cost of bigger size PSV is nothing when compared with downtime of plant. And in such places, client will definately ask to go even for "Double Jeopardy", just to minimize possibility of downtime of plant to zero extent. And I feed nothing wrong in this engineering practice.

#17 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 09 March 2006 - 04:48 AM

Referring to Phil's posting above, my previous posting does not suggest, or even indicate, that system should be operated continuously through the bypass.

We seem to be mixing up two issues:
1. Whether or not the bypass open scenario has to be considered for PSV sizing.
2. Sizing of the bypass line.

The first issue has been discussed at length in this thread.

Regarding the second issue, sizing of the bypass line, I would like to qoute an earlier posting by Phil (in this thread itself) "The purpose of the by-pass is to operate the process while taking the associated controll valve out of service". This being the case, with which I fully agree, the bypass cannot be made more restrictive than the control valve.

With reference to observations made by Ritesh on 'double jeopardy', as also earlier mentions of the same in this thread, a control system failure would typically not qualify as a 'jeopardy' in this context. Please refer API RP 14C (for the offshore E&P facilities atleast). Safeguarding systems would be a lot more simpler if credit for control system failures were to be allowed.

Regards

#18 pleckner

pleckner

    Gold Member

  • ChE Plus Subscriber
  • 564 posts

Posted 09 March 2006 - 12:11 PM

To clarify my stance on the by-pass line, the CV of a full-port manual block valve is usually significantly larger than the CV of a modulating valve. Therefore, one cannot put just a full line size by-pass around the modulating valve and hope not to get into trouble. That is basically why one needs at least a line size smaller by-pass and that is what is historically done in the chemical industry. As far as operating the system with only the by-pass, I wouldn't do it unless it was absolutely necessary for the very reason I stated above, no control.
However, it is often necessary and that is one reason why the by-pass is there, but only as a last resort to keep the system running (making product...making money) untill the control valve can be repaired/replaced. Operations must also be extremely dilligent in keeping the system under constant observation because there is no contol.

The by-pass is also there for start-up purposes when, let's say you may need to do an initial charge of a material or you may need to warm the downstream equiment up to prepare it to accept material. And this is why you can make the line more restrictive.

Saying all this, should one take into account the by-pass opened as well as the associated control valve in a PSV scenario? Let's look at this scenario. Our control valve failed during the midnight shift and the by-pass was opened to allow emergency but limited operation. Near lunch time, the control valve is fixed. The operators are somewhat occupied with lunch on their mind and forget about the opened by-pass. In their haste to get the system back up to full production, they stroke the newly fixed control valve to get it going. Double jeopardy? I think not.

So, yes, this scenario must be taken into account when sizing the relief system.

By the way, this whole discussion should be moved into the Relief Forum and should not be here.

#19 Ritesh Suratwala

Ritesh Suratwala

    Junior Member

  • Members
  • 17 posts

Posted 10 March 2006 - 11:10 PM

To remove control valve for maintainance, you start bypass, close control valve block valves and remove control valve. After maintainance, you fix it at position, open block valve, close bypass valve. This is a common practice has been followed and as a single action. There is no way operator can miss any of step in above process. If it happens, it will be extreem case of carelessness from operator.

Let us believe that it had happened. Now bypass valve and control valve both are in operation and plant is at full capacity mode. At this point, shift engineer must be monitoring control valve opening when control valve is taken in operation. Even if somebody missed to monitor it at that time, during short time it should come in notice. If no one monitors it, it is again case of carelessness from shift engineer.

After maintanance, control valve will not fail very soon. But you are again considering control valve failure at this time only. Now I will stop here sayimg all these under "double jeopardy".

Here, I will highlight one point which I forgot in my past reply. It is not control valve that must be responsible for relief load. It should be either control valve or bypass valve, whichever has higher CV. But again, not both. It is normal practice that Control valve CV is always higher than bypass valve. But final check required.


And if you want to design system for each and every event of carelessness during operation, what will you do for situation when one relief valve is taken out for maintanance without opening inlet/outlet block valves of spare relief valve? :-)

#20 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 18 March 2006 - 05:58 PM

You are right that operational procedures must be followed during maintenance and also think that Pleckner is going a bit overboard in his scenarios for relief valve sizing.

As far as your comment about a relief valve "taken out for maintanance without opening inlet/outlet block valves of spare relief valve," I hope you are aware of the 3 way valves that are marketed specifically for this application. Another (cheaper) way of accomplishing the same is using some kind of a mechanism that ties the two inlet (or outlet) valves mechanically ("mechanical linkage") so that if one valve is opened, the other is closed simultaneously.

Now, I am hoping that Pleckner comments on what happens if a PSV pops just when you are switching from one PSV to the other.

#21 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 21 March 2006 - 12:41 PM

I was actually going to let this thread die but you just had to make me respond.

I was mistaken (oh my gosh, 20 lashes with a wet noodle or if you prefer, a spiked ended whip). I'll go back to my original post and say we did not consider both the by-pass open and the control valve failure; one or the other, that was it and I'll stick with that. And that is why we put in a restrictive orifice in the by-pass line. The by-pass valve had a larger Cv than the control valve and we didn't need the full flow so we just restricted it for the PSV sizing.

I have used all these methods in the past to spare a PSV. It was totally client preference. And I'll ignore that last comment thank you very much.

#22 Guest_Guest_pleckner_*_*

Guest_Guest_pleckner_*_*
  • guestGuests

Posted 21 March 2006 - 12:43 PM

I was actually going to let this thread die but you just had to make me respond.

I was mistaken (oh my gosh, 20 lashes with a wet noodle or if you prefer, a spiked ended whip). I'll go back to my original post and say we did not consider both the by-pass open and the control valve failure; one or the other, that was it and I'll stick with that. And that is why we put in a restrictive orifice in the by-pass line. The by-pass valve had a larger Cv than the control valve and we didn't need the full flow so we just restricted it for the PSV sizing.

I have used all these methods in the past to spare a PSV. It was totally client preference. And I'll ignore that last comment thank you very much.

Phil Leckner
Chief Content Manager
The Chemical Engineers Resource Page

#23 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 21 March 2006 - 12:44 PM

I was actually going to let this thread die but you just had to make me respond.

I was mistaken (oh my gosh, 20 lashes with a wet noodle or if you prefer, a spiked ended whip). I'll go back to my original post and say we did not consider both the by-pass open and the control valve failure; one or the other, that was it and I'll stick with that. And that is why we put in a restrictive orifice in the by-pass line. The by-pass valve had a larger Cv than the control valve and we didn't need the full flow so we just restricted it for the PSV sizing.

I have used all these methods in the past to spare a PSV. It was totally client preference. And I'll ignore that last comment thank you very much.

Phil Leckner
First Content Manager
The Chemical Engineers Resource Page

#24 Guest_Guest_Albert_*_*

Guest_Guest_Albert_*_*
  • guestGuests

Posted 22 March 2006 - 03:09 PM

I asked the same question to a major valve distributor a few months ago. This could quite possibly a jurisdictional issue. For my jurisdiction, inorder to not account for the by pass the by pass valve must be chained/locked closed in order to not account for its discharge capacity.

#25 Guest_Guest_*

Guest_Guest_*
  • guestGuests

Posted 25 March 2006 - 07:56 AM

Regarding bypass valve, in your specific case (Phil Leckner) it must have been a quarter turn valve, which when opened fully could cause an immediate excursion in pressure and cause the PSV to lift. In such a case, I support you for two reasons. For one, most quarter turn valves are "quick opening" since all the operator does is turn it 90 degrees (unlike a globe or a gate valve where you must turn and turn and turn the handle to get full flow). Secondly, the cv of quarter turn manual valves are much larger than globe valves.

I just don't want people to go overboard which is why I wrote in the last comment. I am glad you decided not o go after me on that!


QUOTE (Guest_pleckner_* @ Mar 21 2006, 12:43 PM) <{POST_SNAPBACK}>
I was actually going to let this thread die but you just had to make me respond.

I was mistaken (oh my gosh, 20 lashes with a wet noodle or if you prefer, a spiked ended whip). I'll go back to my original post and say we did not consider both the by-pass open and the control valve failure; one or the other, that was it and I'll stick with that. And that is why we put in a restrictive orifice in the by-pass line. The by-pass valve had a larger Cv than the control valve and we didn't need the full flow so we just restricted it for the PSV sizing.

I have used all these methods in the past to spare a PSV. It was totally client preference. And I'll ignore that last comment thank you very much.

Phil Leckner
Chief Content Manager
The Chemical Engineers Resource Page

QUOTE





Similar Topics