Pressure Testing, Distillation Towers, After Cleaning And Maintenance

pressure test nitrogen vessels distillation fractionation

This topic has been archived. This means that you cannot reply to this topic.
No replies to this topic
Share this topic:
| More

#1 Dave Gone

Dave Gone

    Brand New Member

  • Members
  • 1 posts

Posted 12 July 2013 - 09:43 AM

Hello,

It has been SOP at my refinery to run a pressure test using nitrogen (usually between 5-15psi ) on all vacuum distillation towers, columns and vessels, anytime after they have been opened for cleaning or maintenance.

We have always pumped in a small amount of process oil about 10% to 20% on bottoms level, then filled with the nitrogen and held for one hour while checking for leaks.(wet test)

My question is this.

Recently we have hired a new engineer and she says, we should always do this nitrogen test dry, before any oil has been brought in to the vessel / tower / column.

The wet test has always served us well, but I do see her point of the dry test. 

Is there a best practice or industry standard for this?

Thanks in advance.