Dear Experts!
Please share your thoughts on the points to remember while preparing detailed engineering P&ID from a FEED P&ID.
Thanks
|
Posted 13 December 2013 - 05:35 AM
Dear Experts!
Please share your thoughts on the points to remember while preparing detailed engineering P&ID from a FEED P&ID.
Thanks
Posted 13 December 2013 - 06:06 AM
Yogesh,
This query should be submitted in another forum of this site...
Posted 14 December 2013 - 11:14 AM
Yogesh,
I have attached a PID checklist typical of what I have worked with. A good FEED should include the features shown in the third column, though this quality is sometimes not achieved due to time pressure. During detailed design the features shown in the fourth column are developed, in particular details of vendor packages as received after orders have been placed. The final column (AFC) should include all development during detailed design, including any HAZOP actions on vendor equipment, and ideally with all holds removed (though this is not always possible).
Paul
PID checklist.xls 38KB
257 downloads
Edited by paulhorth, 14 December 2013 - 11:17 AM.
Posted 15 December 2013 - 10:48 PM
Thank you very much gents!
Posted 17 December 2013 - 07:17 AM
Hi Yogesh
The FEED P&ID is detailed in EPC (detailed Engineering).
Some of the examples are
Regards
Syed
Posted 17 December 2013 - 11:51 PM
Thank you syed for your valuable input.
![]() Dynamic Simulation After Feed Flow ReductionStarted by Guest_Kakashi-01_* , 20 Mar 2025 |
|
![]() |
||
Split The Feed Into Two Identical StreamsStarted by Guest_tomr91_* , 16 Mar 2025 |
|
![]() |
||
Effect Of Continuous Blow Down To Boiler Feed WaterStarted by Guest_Dyames027_* , 21 Nov 2024 |
|
![]() |
||
![]() Using Feed Compressor For Start-Up Nitrogen CirculationStarted by Guest_behrouzifar_* , 06 Sep 2024 |
|
![]() |
||
Basic Engineering Vs Detailed EngineeringStarted by Guest_poojabathula369@gmail.com_* , 24 Apr 2024 |
|
![]() |