Hi All
During plant operation need to isolate equipment by process and mechanic isolation by valves,blind,remove spool...etc.Please could you provide me docs or references talk about maintainability during design phase.
|
Posted 21 May 2018 - 07:04 AM
Hi All
During plant operation need to isolate equipment by process and mechanic isolation by valves,blind,remove spool...etc.Please could you provide me docs or references talk about maintainability during design phase.
Posted 21 May 2018 - 05:40 PM
Regarding isolation, a good document is in the following link
http://www.hse.gov.u...iced/hsg253.pdf