Sketch.jpg 50.85KB
4 downloadsDear, hope so that you are all fine and healthy. We are working on the project in Africa, and We have some issues for which we would love to get your expert opinions.
The condensed water, which condensate at the top of the Glycol regeneration column, is sent to water sump S-01. The condensed water at 50°C is then discharged from sump S-01 by two condensate lift pumps P-01 A/B (intermittent pump operation) at existing water line (1) at TP-01 with normal working pressure of 12 barg. Existing water line (1) pressure 12 barg is constant (back pressure for pumps) because the water is through this existing line send to basin B-01 which is at elevation of cc 110 m. This existing line is full of water all the time and create constant backpressure of 12 barg because of elevation.
Our pumps P-01 A/B are vertical centrifugal type with simple mechanical seals, motor power is 22 kW and the pumps motors are sized for end of curve operation. Two pumps are installed (one in operation, the other one in emergency). P-01A/B are design for discharge working pressure of 13.0 barg for flowrate of 6 m3/h (BEP). These pumps can be started and stopped locally using the start and stop pushbuttons and also automatic start and stop from DCS is provided. Generally automatic start/stop is main working regime for this pump. The Condensed Water Sump is equipped with a LT-06 level transmitter. This LT-06 transmitter is used to generate low level LAL-06 and high-level LAH-06 alarms which, if activated, generates the following actions: LAH-06 starts the pump P-01A or P-01B; LAL-06 stop the working pump.
During construction phase of the project client added new connection point TP-02 (because the first existing line (1) is temporary out of service) and connect pumps P-01A/B discharge line to additional existing line (on TP-02) which have normal working pressure 0 barg (the line is empty, and it is connected to existing open basin B-02 near our water sump). If we want to send 6 m3/h of water from our sump S-01 through this new line calculated pressure drop is 1,2 bar. Now client want that we provide solution for pumps P-01 A/B automatic start and stop for both cases.
The pumps must have possibility to send water for both cases (through existing line (1) and additional existing line) with automatic start/stop. The first case (with constant backpressure of 12 barg when we send water through existing water line (1)) this system probably can work and pumps can be automatically started by high level at LT-01 as it is design but for the second one (when water is sent through additional existing line) the pumps cannot be started automatically.
During commissioning phase pumps P-01 A/B are functionally tested (4h work each) by manual start with closed discharge valve. Because existing line (1) with backpressure of 12 barg is out of function at that time we must send water to the new line added by client. Pressure at this line is 0 barg and to reach pump working point (6 m3/h and 13 barg) we slowly opening pump discharge gate valve to reach 13 barg pressure at pump discharge. The gate valve opening was only cc 7-8%. We understand that this is not good work, that gate valves need to be in on/off position etc. but anyway, we must do it even if we had possibility to have bigger problems. The pumps are worked without problems during this 4h testing.
Now we are thinking about possibly solution for this issue. We think that the best solution is to install self-regulating pressure control valve which will control upstream pressure (pump discharge pressure) and keep it at constant value of 13 barg. During automatic start of the pump self-regulating pressure control valve will be in close position and it will start to open after pump is on. Any idea or suggestion is highly appreciated. In attachment you can find the drawing sketch of the system and for any additional questions, clarifications or information we are happy to provide them.
Best regards
Edited by suljaga, 24 August 2021 - 05:00 AM.