Chlorine is contineously dosed at a constant rate in once through flow type water systems for eg condenser cooling water systems.
The systems comprises of 900kg chlorine tonner at 10 kg/cm2, supplying chlorine to evaprator whereby chlorine is heated up to a temperature of 70-80 deg celcius in coils immersed in water bath. The chlorine outlet in vapour form is reduced to 2kg/cm2 through PRV & then through a flow regulator injected in ejector suction, motive water to ejector is drawn from system & fed back to the system.
My questions are
Why there is a need for evaporating the chlorine before injection?
How will come to know that tonner is emptied, the PG on tonner when taken in service shows 10 k/cm2.
generally two tappings are provided on tonner (kept in horizontal cylinder orientation) upper & lower, what is the significance.
regards
|

Water Chlorination Systems
Started by rsk, Sep 18 2008 10:34 PM
No replies to this topic
Share this topic:
#1
Posted 18 September 2008 - 10:34 PM
Similar Topics
![]() Steam Carrying Liquid From The Sour Water Stripping TowerStarted by Guest_kaidlut_* , 12 Sep 2024 |
|
![]() |
||
![]() Steam Sparger In Atmospheric Water TankStarted by Guest_owe_* , 16 May 2025 |
|
![]() |
||
Water Hammer Study: Hysys Dynamics Vs PipenetStarted by Guest_powerox29_* , 07 Apr 2025 |
|
![]() |
||
Water TreatmentStarted by Guest_not_mikhail_* , 01 Apr 2025 |
|
![]() |
||
![]() Transfer Water By Gravity - Maximum Velocity CriteriaStarted by Guest_56200358_* , 05 Mar 2025 |
|
![]() |