Jump to content



Featured Articles

Check out the latest featured articles.

File Library

Check out the latest downloads available in the File Library.

New Article

Product Viscosity vs. Shear

Featured File

Vertical Tank Selection

New Blog Entry

Low Flow in Pipes- posted in Ankur's blog

Overall Heat Transfer


This topic has been archived. This means that you cannot reply to this topic.
2 replies to this topic
Share this topic:
| More

#1 chau

chau

    Veteran Member

  • Members
  • 47 posts

Posted 23 February 2009 - 12:04 AM

Dear all

I begun to calculate the overall heta transfer for WHR boiler . I pose to perceive what are the critical factor to be taken into consideration while calc the same . Notebly the heat transfer is shell and tube type and medium is fluegas and organic fluid

Thanks for being so understanding.

MONTEK

#2 smalawi

smalawi

    Gold Member

  • ChE Plus Subscriber
  • 138 posts

Posted 23 February 2009 - 05:51 AM

Hi,

can you put more info on process steam type or composition ? are these fouling ? process pressure / temperatures ?

also TEMA type of your Whb

cheers,

sm

#3 chau

chau

    Veteran Member

  • Members
  • 47 posts

Posted 23 February 2009 - 06:00 AM

QUOTE (smalawi @ Feb 23 2009, 05:51 AM) <{POST_SNAPBACK}>
Hi,

can you put more info on process steam type or composition ? are these fouling ? process pressure / temperatures ?

also TEMA type of your Whb

cheers,

sm


Dear sir

Thanks for your generosity

Input Data of flue gas

1) Flue Gas SOURCE-1(PRE-HEATER) SOURCE-2(COOLER OUTLET)



Flow 259701 Nm3 / Hr 159619 Nm3 / Hr



Inlet Temperature 324 Deg C 382 Deg C

(to boiler)



Dust content 12 g/m3 15g/m3


Above is the input data of flue gas to boiler , as there is two source point of heat in cement plant. I had complied the operating parameter of same

As inquired by you for TEMA design , lets be frank i dont know the significance of using TEMA in boiler. Kindly enlighten me about the same

Objectively we may use the organic fluid. Decisively the operating parameter will be normal , since the generation is of 2MW Power.

Taking above in consideration , kindly have me your response