|

Precomm. And Commissioning
#1
Posted 26 April 2010 - 07:55 AM
(1)What is per-Commissioning activity and what is commissioning activity?
(2)On what basis we will decide that this fluid will require hydro test and pneumatic test??Generally somewhere i read that In gas service pneumatic test will done and in liquid service hydro test will be done.is it true or is it some criteria based on that this will decide.
(3)On what basis hydro and pneumatic pressure will decide?
(4)What are parameters that will decide plant performance?
#2
Posted 26 April 2010 - 09:21 AM
I Want to ask 4 basic questions.
(1)What is per-Commissioning activity and what is commissioning activity?
(2)On what basis we will decide that this fluid will require hydro test and pneumatic test??Generally somewhere i read that In gas service pneumatic test will done and in liquid service hydro test will be done.is it true or is it some criteria based on that this will decide.
(3)On what basis hydro and pneumatic pressure will decide?
(4)What are parameters that will decide plant performance?
Regarding hydro and pneumatic pressure test:
Well, I'm not mechanical engineer but I think that pneumatic test should be used only in cases where any water presence in the system is not allowed. I would avoid that anyway. In case of failure it causes horrible destruction. Special safety precautions must be applied. During hydro test, in case of equipment failure, water just go out the equipment. Read further in ASME codes.
Regards.
Edited by wojtar, 27 April 2010 - 02:13 AM.
#3
Posted 28 April 2010 - 12:47 AM
I Want to ask 4 basic questions.
(1)What is per-Commissioning activity and what is commissioning activity?
(2)On what basis we will decide that this fluid will require hydro test and pneumatic test??Generally somewhere i read that In gas service pneumatic test will done and in liquid service hydro test will be done.is it true or is it some criteria based on that this will decide.
(3)On what basis hydro and pneumatic pressure will decide?
(4)What are parameters that will decide plant performance?
(1)Pre commissioning activities include all the leak tests , flushing , dry outs etc. all the activities that are done before first start up of a unit takes place. The activities during first start up (after all pre-commissioning activities are completed) are commissioning activities.
(2)As far as i know any service where moisture content cannot be tolerated pneumatic test is done
(3)Normally hydro testing pressure is roughly 1.5 times (someone plz confirm) the design pressure of a equipment
(4)Plant performance can be characterized with conversion , energy efficiency etc. as parameters
Hope this helps
Gaurav Sharma
#4
Posted 28 April 2010 - 03:34 AM
(1)Pre commissioning activities include all the leak tests , flushing , dry outs etc. all the activities that are done before first start up of a unit takes place. The activities during first start up (after all pre-commissioning activities are completed) are commissioning activities.
At the EPC company I worked for the shift from pre-commissioning to commissioning activities was when the plant was declared "mechanical complete". At that point of time the plant responsibility shifted from the construction manager to the commissioning manager. Commissioning ended when the plant was declared "Ready For Start Up". At that point of time the plant responsibility shifted from the commissioning manager to the plant manager.
Edited by gvdlans, 28 April 2010 - 03:35 AM.
#5
Posted 28 April 2010 - 10:30 PM
(1)Pre commissioning activities include all the leak tests , flushing , dry outs etc. all the activities that are done before first start up of a unit takes place. The activities during first start up (after all pre-commissioning activities are completed) are commissioning activities.
At the EPC company I worked for the shift from pre-commissioning to commissioning activities was when the plant was declared "mechanical complete". At that point of time the plant responsibility shifted from the construction manager to the commissioning manager. Commissioning ended when the plant was declared "Ready For Start Up". At that point of time the plant responsibility shifted from the commissioning manager to the plant manager.
I am currently working in a refinery, here we define pre-commissioning activities as various activities to be performed after the mechanical completion to prepare unit for start up, and unit is said to be commissioned once we get on spec product
#6
Posted 30 April 2010 - 03:39 AM

c) Pressure now a days is usually 1.25 times minimum of the design pressure, lower pressures is sometimes prescribed in case of Hot equipment - Note that HT or PT is not a static test, we raise the pressure gradually watching the system at each defined increment, don't want any mishaps
d) Parameters of plant performance vary with contract and process, some examples are - compliance to all air/water emission norms, local government laws, product quality and quantity, energy norms, safe operating range (say 40 % to 105 %)- safe shutdown system test, capability of control system in milli seconds, smooth control etc etc- this is a big issue, some of the parameters we cannot even practically verify. I hope you find this useful
Similar Topics
Suggestion For Reference Book For Process Plant CommissioningStarted by Guest_JKM_* , 17 Feb 2023 |
|
![]() |
||
Charcoal Filter CommissioningStarted by Guest_Abm_* , 20 Jul 2022 |
|
![]() |
||
Pre Commissining & CommissioningStarted by Guest_Jaldhi_* , 08 Mar 2022 |
|
![]() |
||
Refinery CommissioningStarted by Guest_Divid Kelin_* , 20 Apr 2021 |
|
![]() |
||
Commissioning Activities: Special TestsStarted by Guest_Uchihahaha_* , 24 Nov 2020 |
|
![]() |