Closed Drain Drum Size Calculation

slop tank cds blowdown tank

This topic has been archived. This means that you cannot reply to this topic.
3 replies to this topic
Share this topic:
| More

#1 Christiano

Christiano

    Junior Member

  • Members
  • 21 posts

Posted 17 October 2012 - 08:12 AM

Hi,

For a typical EXISTING on-shore degassing station, any inputs on sizing the closed drain durm (slop tank). ??


Edited by Raj India, 26 April 2013 - 03:01 AM.


#2 kushal.raval

kushal.raval

    Brand New Member

  • Members
  • 7 posts

Posted 17 October 2012 - 09:08 AM

The slop system to be sized wrt two points:
1) Maximum upstream flow/volume in to the slop system. e.g. single largest equipment maintenance scenario. In this, you have to drain all the equip. content to slop tank.
2) Downstream slop processing or send out facility limitation. e.g. you should be decant the vessel by optimized time (may be 4 to 6 hrs), so that vessel may ready for receiving next load.

#3 Vihaan

Vihaan

    Brand New Member

  • Members
  • 1 posts

Posted 18 February 2014 - 03:45 AM

Can anybody tell me, how we set high level, high high level and nozzle elevation (if side entry). Also height from high high level or nozzle top to the top TL. This is regarding horizontal underground drain drum.

Please post your opinion.

Thanks

Vihaan.



#4 Steady

Steady

    Junior Member

  • Members
  • 19 posts

Posted 19 February 2014 - 02:17 AM

Vihaan

 

As 'Kushal.Raval' said in the post, you first need to to know the maximum working volume for the drum. Put some margin on the working volume. This volume should accomodate in LAL - LAH. Think it as an intervative process. Choose a D and L according to the ratio (if any) in the standards that you are currently following.

While chosing L; think of all the nozzles, connections to vent/flare and pump (if you have it) .

LSHH is generally 100mm or 150 mm above the LAH ---this should be in your standards.

LSLL is generally selected on the basis of providing minimum NPSH to the pump in case of a submerged suction vertical pump. If there is no pump, then specify LSLL 100-150mm below LAL.

Do you have a boot?

LSLL can be in the boot or in the main drum.

 

Hope this helps.


Edited by Steady, 19 February 2014 - 02:18 AM.