Hi
I am a process engineer and I want to design acid gas flare knockout drum which is Horizental in crude refinery. according to API 20-30 minutes holdup time is required for LLL-HLL but for some cases, it was 6-7minutes. I want to determine: drum diameter,length, HLL and LLL positions.
I will appreciate you if you give me some help.
|
|
Design Of Acid Gas Flare Knockout Drum
Started by rasprocess, Oct 30 2012 04:46 AM
4 replies to this topic
Share this topic:
#1
Posted 30 October 2012 - 04:46 AM
#2
Posted 30 October 2012 - 07:32 AM
Dear rasprocess,
Please go through API 521. There is an example for the KOD ( Flare Knock out drum ) Sizing calculation.
I have develop spread sheet for KOD sizing. Personally suggest make your own spreadsheet. You will come across so many question.
Regards,
Please go through API 521. There is an example for the KOD ( Flare Knock out drum ) Sizing calculation.
I have develop spread sheet for KOD sizing. Personally suggest make your own spreadsheet. You will come across so many question.
Regards,
#3
Posted 30 October 2012 - 10:15 AM
Be careful using the procedure of API 521. Whenever you finish sizing it you can check adequacy with software at www.bobby-strain-group.com. There is also a program demo for the best sizing program around. Take a look at it and if you study the results carefully, you can gain insight into the proper procedure. Size as a vertical drum to get the recommended nozzle sizes for the inlet and vapor outlet. You need to gain enough understanding of the API guide to have confidence in your work. Always double and triple check anything you get from someone else, including me. Give careful consideration to liquid holdup; better to have too much than too little. Good luck.
Bobby
Bobby
Edited by Bobby Strain, 30 October 2012 - 09:49 PM.
#4
Posted 05 November 2012 - 01:44 PM
Dear rasprocess,
You can also go through Shell DEP procedures for sizing flare KODs. It defines gas load factor, value of which you have to decide based on for how much micron size you are sizing your flare KOD.
You can also go through Shell DEP procedures for sizing flare KODs. It defines gas load factor, value of which you have to decide based on for how much micron size you are sizing your flare KOD.
#5
Posted 05 November 2012 - 03:36 PM
Alok,
You frequently refer to Shell DEP. But this is not a public document. It's intended for use on Shell projects, and probably says so in the document.
Bobby
You frequently refer to Shell DEP. But this is not a public document. It's intended for use on Shell projects, and probably says so in the document.
Bobby
Similar Topics
Scrubber DesignStarted by Guest_syamsundar_menon_* , 02 Jul 2018 |
|
|
||
Lpg Plant DesignStarted by Guest_betulche_* , 08 Mar 2026 |
|
|
||
Air Separation Plant DesignStarted by Guest_adda_* , 03 Mar 2026 |
|
|
||
Beginner Question: Inlet Separator Design In Aspen Hysys (Natural Gas,Started by Guest_NewEng2030_* , 12 Feb 2026 |
|
|
||
Condenser DesignStarted by Guest_Kentucky08_* , 07 Dec 2025 |
|
|

FB