Please advice if in a revamp plant hydro testing needs to be done again if design pressure of the system has increased due to new shut off conditions of new pump being installed in the system.
Earlier design pressure of the system is 6 barg, hydro test pressure 1.5 times so 9 barg.
New design pressure is 7.2 barg based on new operating condition and new pump shut off. Can an exception be taken on the grounds that new design pressure is still less than test pressure and It is 150 pound rating piping.
|
|
Hydro Testing Required Again If Design Pressure Is Increased
Started by Sumun, Jun 04 2016 05:22 AM
1 reply to this topic
Share this topic:
Similar Topics
Hello, Design Of Natural Gas Liquefaction Processes.Started by Guest_guoyinyanliner_* , 21 May 2026 |
|
|
||
The Basis Of Calculation To 3% Pressure Loss At The Inlet Of PressureStarted by Guest_phoenixmoca_* , 14 Mar 2026 |
|
|
||
Absorber And Stripper Design - Eqbm Data?Started by Guest_ChemEngBoy26_* , 03 May 2026 |
|
|
||
Adsorber Design Essay QuestionsStarted by Guest_Kahirn_* , 10 May 2019 |
|
|
||
Pressure BuildupStarted by Guest_Yankee_* , 31 Mar 2026 |
|
|

FB