Tank Inspection

inspection

No replies to this topic
Share this topic:
| More

#1 vaseline

vaseline

    Brand New Member

  • Members
  • 1 posts

Posted 11 August 2020 - 03:37 PM

A 10 year old reactor, the jacket of the reactor has not been used for 3 years.  Client wants to re-connect the jacket with steam ( 8 barg saturated).  Jacket design condition is 10 barg 250 C stainless steel.

 

We suggest to do inspection before let steam going through. Client doesn't think it necessary is. There is an inspection report from 4 years ago, but it is only about the reactor not jacket. 

 

 

Is there a regulation or standard explaining this issue? 

 

 

Any advices? 

 