In our refinery we have to tanks for flushing oil which is used for flush the Hydrocraker and diesel unit
Flushing oil required for Hydrocraker is 16000m3/hr
Flushing oil required for Diesel unit is 12000m3/hr
Each of tanks capacity around 4800m3
How much required time to fill up the tanks ?
The capacity of tanks not enough so how we can solve this issue there is any idea for that ?as you know flushing it will take time
|


Refinery Start Up
Started by Divid Kelin, Apr 13 2021 08:51 AM
1 reply to this topic