Dear Qalander, herebelow are some justifications of the issues, subject of course to any further comments:
(from 26th May 2010 Post)
2. 10% over design pressure is acceptable for equipment, if of short duration. I suppose that
20% is similarly acceptable, for equipment hydraulically tested at 150% of design pressure (as it happened in the past).
3. A tightly closed valve is acceptable to "isolate" different design pressures. Nevertheles, in addition to mentioned risks (of loosing protection), the valve may "detect" high pressure late (that is after it has passed through it).
I can not agree to or endorse your opinion as Highly Risky and Unsafe.
Answer: Allowable 20% margin (for short duration) was
supposed, seeing that few years ago PSVs were developing full flow at 20 or 21% overpressure in case of fire. And equipment was then hydraulically tested at 150% of its design pressure.
Nowadays PSVs are set to develop full flow at 10% overpressure even in case of fire and equipment is hydraulically tested usually at 130% of design pressure.
The real question concerns short term allowable overpressure and clarifications would be welcomed, if possible with reference to supporting codes. Above said is applicable to local Refineries, but I do not know the supporting codes (over here these do not make a responsibility of Process Dpt in general).
Heat exchangers (per API) make an example, concerning tube rupture case. Allowable (without need of PRV) short term pressure of the low pressure side equals its hydrostatic test pressure (hence the rule of 2/3 in the past versus 10/13 nowadays).
As read in WWW, allowable overpressure seems to be 0-10% in case of water hammer (depending on code), probably because relevant calculations cannot be very precise.
10% short term overpressure is considered allowable for equipment here.
(From today's just preceding post)
1. You mean the line injecting water into the crude upstream exchangers. We will not act on this existing line, transferring about 20% of total water flow. I guess it intends to "clean" the crude line, reducing exchanger scale.
2. The header contains crude oil heated in a series of exchangers and then going to desalter. We try to upgrade discharge line (with connected equipment) to 36 Barg design pressure (same as header), to avoid any problem. Cut-off valve combined with check valve could be a solution to overpressure (see previous posts), but since the valve is electrically or pneumatically motivated there are questions about its reliability. So the cut-off valve will not aim at overpressure protection, but rather to stop crude back flow to water network in case that the water feed pump stops. In this specific case, operators assure that there is enough time for the valve to close on low pump flow, which seems reasonable (valve and crude header have a distance ~40 m).
Again 1) refers to wash water Primary injection point
Argument in 2) for secondary water injection point
A)Dependence on operators for cut-off and
B)accepting 40 m distance sort of sufficient to safeguard do not seem really reasonable enough to be Safe, Reliable and Trustworthy sustainable operations and possible water pump& Drive's numerous failures along with reversed rotation and gross level water circuit crude oil Contamination are Foreseeable.Answer: The concept is that the cutoff valve closes automatically on
low water flow (close to water pump min flow) while the water pump is still operating. Reverse flow of crude meets two check valves before contacting the cutoff valve.
Worst condition would be at sudden stop of water pump, when the cutoff valve is still closing. Still crude has to pass through 40 m pipe with two check valves, and this only while cutoff valve does not get fully closed.
Edited by kkala, 29 May 2010 - 06:58 AM.